Access Access Permit# 24-06OL, UID# 13017
App. Status: Active
Clay County Highway Department
2951 41 1/2 Street South
Moorhead, MN 56560
Phone: 218.299.5099
Fax: 888.259.8757
highway.department@co.clay.mn.us
 

Duration

This entrance is: Permanent

Entrance

Entrance Type: Residential
When is the entrance needed by:
05/03/2027

Location

Direction from road: S
County Road No.: 12
specific road, landmark, or intersection: Hwy 31 and Cnty Rd 12
Direction from specific road, landmark, or intersection: E
Miles: .35
Address or PID: 13.025.0100
City: Hawley
Type of building being constructed: Residential
Present number of driveways:
0
Distance from nearest driveway (enter 0 if N/A): 0 feet 0 inches

Property

Description: New home

Applicant

Applicant:
Name:
Darrel Slette
Phone:
(218930 - 0027
Email:
darrelslette67@gmail.com
Address:
22485 40th Av S
Hawley MN 56549

Property Owner

Property Owner:
Name:
Andrew Slette
Phone:
(218930 - 0074
Address:
22485 40th Av S
Hawley MN 56549

Contractor

Contractor:
Name:
Andrew Slette
Phone:
(218930 - 0074
Address:
22485 40th Av S
Hawley MN 56549

Sketch

Work Description

Work Description:
Construct approach and driveway to new home construction site

Terms

General
  • I, We, the undersigned, herewith make application for permission to construct the Access Connection at the above location, said Access Connection will be constructed to conform with the regulations of the Department of Highway and to any special provisions included in the permit. It is agreed that all work will be done to the satisfaction fo the Department of Highway. It is further agreed that no work in connection with this application will be started until the application is approved and the permit issued. It is understood that this permit is conditioned upon replacement or restoration of the highway to its original or to a satisfactory condition. It is further understood that this permit is issued subject to the approval of local city authorities having joint supervision over said street or highway.

  • At minimum, applicants shall attach a sketch of the property which shall include identification of existing and proposed Access Connections in relation to any County Highways; and such sketches shall be drawn to scale when required by the Engineer. See Section 8.3.6 of the County Development Code for specific Access Permit submittal requirements.

  • The applicant should install a lath or stake at the location desired for the center of the proposed opening for accuracy during inspection prior to approval. The highway department will discuss the location with the applicant if it needs to be moved.

  • The Highway Department will inspect the location for safety, sight distance, proximity to other access openings and drainage requirements. The applicant will be notified of approval and/or any necessary requirements. All Access Connections will be reviewed for compliance with the County's Access Management Policy (see County Development Code Section 8.3.6).

  • If the Access Connection requires a drainage structure, the County will provide one culvert per quarter section in rural areas. In urban areas the County will provide one culvert per residence. The applicant will be responsible for installing the culvert the County has provided. The Highway Department will determine and order the appropriate size and length of culvert required.

  • If the Access Connection is for a residence or business receiving mail at the permitted location, Clay County will provide an approved mailbox support at the applicant's expense. Upon request, the mailbox support will be delivered at the same time as the culvert. The applicant will be required to install the support.

  • The cost of constructing the Access Connection is the responsibility of the applicant. This includes any fill or excavating that may be required. In urban areas, it is the responsibility of the applicant to remove and replace curb and gutter at the Access Connection location.

  • When construction of the Access Connection is completed in accordance with specifications and special provisions noted on the permit, the applicant shall notify the Highway Department for final inspection. The permitted Access Connection will not be considered complete until all disturbed areas have been fine graded, top soiled and seeded. All work is to be completed within 90 calendar days after receipt of the approved permit or as otherwise specified in the Access Permit. For additional information on permit duration standards, see Section 8.3.6 within the County Development Code.

  • Prior to beginning any excavation work, Minnesota Law requires the applicant or their contractor to contact Gopher State One-Call for locations of underground utilities. They can be reached at 800-252-1166.

  • Whenever work on the traveled portion of the roadway or shoulder is necessary, proper traffic control devices shall be furnished by the applicant and shall be in accordance with the most current edition of the Minnesota Manual on Uniform Traffic Control Devices, which is also available for review at the Clay County Highway Department at the applicant's request.

  • Please note that all equipment which may damage surfaced roadways is prohibited from use on the roadway. Any damage to the roadway surface due to loading, unloading or operating such equipment will be assessed to the applicant. Please help us protect our highway surfaces.

Invoice #12281 (04/22/2024)

Charge Cost Quantity Total
Non-Taxable
added 04/22/2024 9:24 AM

This fee includes the cost of two required inspections; one prior to construction and one after completion.

$125.00 x 1 $125.00
Grand Total
Total $125.00
Payment 04/22/2024$125.00
Due$0.00
Action: Print  

Special Provisions

-The proposed home access shall be constructed approximately 1446' East of the CSAH 12 and CSAH 31 intersection, South of CL.
-Clay County will furnish and deliver 18'' x 36' Corrugated Metal Pipe.
-Applicant shall install pipe at their own expense.
-Applicant must maintain existing drainage by surveying ditch bottom elevations.
-The top width of the proposed driving surface will be a maximum of 28', with a 4:1 Slope down the sides.
-Access to be built matching road grade or slightly below grade to allow for maintenance operations.
-Applicant must contact the Clay County Highway Department to review the new entrance installation after project is complete.
-Applicant is responsible for contacting the Watershed for any additional permits needed.

Approvals

ApprovalSignatureOptions
ApplicantDarrel L. Slette - 04/22/2024 10:05 AM
1a7ef5237f708d5ef182fdecd7126a5c
26ba62d8aa02f791227f29366ba32622
 
#1 Engineering TechnicianShane M. Finck - 06/03/2024 8:08 AM
2a65a2b7e6f98522938ed5c7f0a7ab3e
61fea40481b81bba05ae38d7fe38dc03
 
#2 Assistant County EngineerAlex Soyring - 06/03/2024 8:52 AM
a3ee53b62adc34d6932427ba0e38abcb
93def12b516ea3183c0db6779a29c508
 
#3 County EngineerJustin P. Sorum - 06/03/2024 10:20 AM
592a59aae83ef10d16da6d2e57ff670a
5ff11964aa6b480670c33a3ffc90695c
 
Permit has been approved. All signatures have been obtained.
Powered by